On a periodic basis, you need to Post to record any changes to task deliverable budgets and task dates. Cost budgets and task dates will inevitably change.

When budgets or dates are changed, it impacts the revenue associated with a projects project by moving revenue earlier or later based on delays or accelerations in project deliverables. In our exampleFor example, if Deliverable 2 was were to be moved out to mid-December from the original date of the end of November. Because of , the delay , would cause additional labor costs are to be incurred to complete the deliverable. Note the change in project costs and the deferral of revenue into the Project costs would change and revenue would be deferred into December due to the increased labor and delays on the project.