Question

How do I re-baseline the budget if a task is put on hold temporarily, without incorrectly reporting this gap in the Earned Value Report?

Solution

If a project or a task is placed on hold, the original end date should be modified to end the current project with an update to the budget that reflects the expected amount of work to be accomplished for this period. A new task can be created with the new begin date after the hold period so the hold period is not reflected in the Earned Value Report.