Question

Can I allow future charges on a Vacation or PTO project and still be DCAA compliant?

Solution

The "Allow Future Charges" setting is enabled on a project by project basis, therefore PTO projects can allow future charges, while worked projects can  limit the ability for users to charge future time. The project manager can disable the Allow Future Charges button on the project Time tab for the worked projects.


Additional Information

Help Docs - Project Profile